DevelopmentTop story
Valor Energy closes on its Logan Avenue site and plans a $700 million data center in Youngstown
Valor Energy plans $700 million in phases at one Logan Avenue site
- $700 million
- in planned investment, in phases
- $200 million
- for the first phase
- $3.6 million
- agreed price to acquire Glorious Star
- 18 MVA
- of site power capacity from Ohio Edison
Sources: Tribune Chronicle, WFMJ
If you've driven past Logan Avenue and wondered what's next, here's the answer. Valor Energy Inc., based in New York, plans to invest $700 million to turn a former Parker-Hannifin facility there into an AI data center. The company said Monday it has finished buying Glorious Star LLC, the business on the site.
The Youngstown/Warren Regional Chamber says the estimates are preliminary and not committed funding. If the full $700 million comes, Chamber CEO Guy Coviello said it could be the city's second-largest investment in nearly a century, behind Vallourec's $1.05 billion expansion.
- Site: 1911 Logan Ave., in the 3rd Ward
- Public incentives: none sought, including tax abatements
- Still needed: development work, permits, approvals, equipment and financing
The Logan Avenue site covers 30,888 square feet
Floor area of the Logan Avenue site, beside places you know
7 basketball courts would fit inside the Logan Avenue site
Source: Tribune Chronicle
View as table
| Floor area | |
|---|---|
| The Logan Avenue site | 30,888 sq. ft. |
| A football field | 57,600 sq. ft. (end zones included) |
| A basketball court | 4,700 sq. ft. (NBA size) |
City officials said last month they weren't told of the plan when it was first reported. Mayor Derrick McDowell says he's neither for nor against data centers but wants a fair deal. “They didn't have to tell us,” he said of Valor. “But we have legal responses. We have zoning.”