Mahoning CountySaturday, November 28
A McDonald coalition asks council to lift the village's data center moratorium
The Daily Youngstown team
The Mill Opportunity Coalition wants McDonald Village Council to lift its data center moratorium so Oppidan's proposed campus on the former McDonald Works steel site can get a full public review. Council voted unanimously Sept. 16 for a 12-month moratorium. The coalition says lifting it wouldn't approve the project. It would let the village consider a community benefits agreement, zoning ordinance or conditional use permit.
Oppidan's plan would bring $5.2 million a year in property taxes
- $5.2 million
- a year in property taxes once complete, per Oppidan
- $64,769
- a year the site generates now
- $10-50M
- estimated cleanup cost Oppidan says it would pay
Source: Tribune Chronicle
- Size: down nearly 50% in square footage
- Tax breaks: none sought, per Oppidan's FAQ
- Noise: 55 decibels or less at the property line
- Closest home: about 900 feet away
Oppidan first proposed nine to 12 data center buildings and has since scaled back to five. Mayor Ray Lewis said he's reviewing the letter and that he and council "will continue to listen to every concern."
The mill site's future has been in play since the steel plant closed
- July 2024McDonald Steel shuts down, facing more than $60 million in needed upgrades.
- Sept. 15Oppidan holds an open house on its data center proposal.
- Sept. 16Council unanimously votes for a 12-month data center moratorium.
- Nov. 27The coalition's letter asks council to lift the moratorium.
Sources: Tribune Chronicle, WKBN.com
Sources: Tribune Chronicle, WKBN.com