DevelopmentSaturday, November 28
Valor Energy closes on the Logan Avenue site it wants to turn into an AI data center
The Daily Youngstown team
Valor Energy Inc. says it has completed its purchase of Glorious Star LLC, a company that operates on Logan Avenue. Valor says it plans to invest $700 million in AI data center infrastructure there. The Mahoning County Auditor's Office categorizes Glorious Star as a bitcoin mining operation. Valor is calling the venture the Youngstown Project.
The Glorious Star site covers 30,888 square feet
Floor area of the Glorious Star site, beside places you know
7 basketball courts would fit inside the Glorious Star site
Source: Tribune Chronicle
View as table
| Floor area | |
|---|---|
| The Glorious Star site | 30,888 sq. ft. |
| A football field | 57,600 sq. ft. (end zones included) |
| A basketball court | 4,700 sq. ft. (NBA size) |
- Power: about 18 MVA through a 23 kV Ohio Edison connection
- Valor's executive offices: New York
Dave Nichols, an adviser to Valor, said the site's existing infrastructure "may help reduce certain development requirements," though conversion will need permits, approvals and financing.
Valor plans $700 million, with $200 million in the first phase
Sources: WFMJ, Tribune Chronicle
View as table
| Value | |
|---|---|
| Purchase price | $3.6 million |
| Initial phase | $200 million |
| Planned investment | $700 million |
City officials said they weren't told of Valor's plan when it was first reported. Mayor Derrick McDowell says he's neither for nor against data centers but wants a fair deal for the city: "But we have legal responses. We have zoning." Calls to him and his representative weren't returned. WFMJ reports that pushback is growing across the Mahoning Valley.
Sources: Tribune Chronicle, WFMJ